Why prices keep climbing, what PJM and FERC are doing about it, and where data centers fit in

PJM doesn’t just sell electricity; it also runs a separate “capacity market” that pays power plants in advance to promise they’ll be available on the hottest or coldest days of the year, like a standby fee. What that market pays flows straight into the capacity charge built into your electric supply charges. Right now, that market is under real strain: demand is growing faster than new power plants are getting built, auction prices have hit their ceiling three times in a row, and federal regulators are publicly pressuring PJM to fix its process. This article walks through what’s changed, what’s being proposed, and why large new electricity users, especially data centers, are driving most of it.

 

The Core Problem: Demand Is Outrunning Supply

PJM projects it could be short 50-60 gigawatts of capacity over the next decade, roughly enough electricity to power somewhere between 35 and 45 million typical homes. The main driver is large new load growth, especially data centers. New power plants simply aren’t being built fast enough to keep up, and the queue to connect new generation to the grid, historically the biggest bottleneck, needs its own overhaul. This isn’t a short-term supply crunch; it reflects a structural shift that PJM’s traditional three-year-ahead planning cycle wasn’t designed to absorb quickly.

 

The Latest Auction: Still Short, Even at the Price Cap

PJM released the results of its most recent capacity auction, covering the 2028/2029 delivery year, on July 14, 2026. Power plants and demand-response programs committed 138,318 megawatts of capacity, and utilities that opted out of the auction (the FRR entities, defined above) committed another 10,864 megawatts on their own. Combined, that’s 149,182 megawatts against forecasted peak demand plus a safety margin.

Even so, the auction came up 6,831 megawatts short of PJM’s reliability target, and prices hit the $325 per megawatt-day price cap across the board, meaning the market wanted to pay even more, but the price collar wouldn’t let it. More capacity cleared than in the prior auction (mostly gas and solar, while coal declined as some units convert to gas), but still not enough. That gap is exactly what PJM’s new “backstop” procurement (explained below) is meant to help close. The next auction, for 2029/2030, is scheduled for December 2026.

 

Three Reform Tracks

PJM is working on three fronts at once to address the shortfall. Here’s the shape of each:

Reform track

What it does

Status

1. Price collars

Narrows the range auction prices can land in, so costs are less volatile, and keeps a few retiring plants online a bit longer as a bridge.

In effect through 2027/2028; extended by FERC in April 2026

2. Faster new supply

Fast-tracks “shovel-ready” power projects through the interconnection line, and lets underused grid connections be shared between projects.

Underway

3. Structural reset

A May 2026 PJM proposal to rethink the whole capacity market design, longer-term contracts, different rules for large new loads, and less reliance on the capacity market overall.

Proposal stage; FERC pressing PJM on pace

 The third track is the big one. In a May 6, 2026 white paper, PJM laid out three possible long-term redesign paths: locking in longer-term supply commitments, treating large new loads differently from everyday ratepayers when it comes to reliability obligations, and shifting more cost recovery toward the day-to-day energy market rather than the once-a-year capacity auction.

 

Federal Regulators Are Pushing Back on the Pace

This reform push isn’t happening quietly. At PJM’s May 12, 2026 annual meeting, FERC Chairman Laura Swett said the region faces “historically unprecedented demand” and needs new generation now, while also criticizing PJM’s decision-making process as too slow and too easy to stall through procedural objections. FERC has since called a technical conference for July 23, 2026, focused specifically on how PJM’s governance and stakeholder process work. FERC can’t rewrite PJM’s governance directly, but it does have to approve the market rules PJM eventually files, which gives it real leverage over the outcome.

 

The Data Center Factor

Data centers are the common thread behind nearly every reform effort here, and PJM’s most concrete near-term response to them is something called the Reliability Backstop Procurement, or RBP.

The idea has evolved. PJM’s original April 2026 concept was a one-time push to secure close to 15 gigawatts of new capacity by 2031. After months of stakeholder negotiation, PJM’s stakeholders voted on June 30, 2026, to endorse a specific version: a two-part backstop procurement capped at $555 per megawatt-day, built around a “registry” where large electricity users tell PJM in advance how much capacity they’ll need procured on their behalf. A related proposal that would have let PJM cut power to large loads during shortages, called “Connect and Manage”, was rejected by stakeholders.

Two things matter most for institutional and commercial accounts:

  • The registry model is designed to bill the costs to the large loads that create the need for new capacity, not to spread them across everyday ratepayers. Consumer advocates like the Natural Resources Defense Council have welcomed this.
  • This is explicitly framed as a bridge, not a replacement for the main annual auction. It’s meant to get new supply built faster while the bigger structural reforms above get worked out.

 The June 30 vote was advisory only, and it’s now up to PJM’s board to finalize a proposal. PJM’s CEO, David Mills, has said PJM plans to file both the backstop procurement and the rejected Connect and Manage proposal separately with FERC in July 2026, aiming to lock in backstop commitments before the December 9, 2026 auction.